Bifold gate installation and commissioning

What to prepare on site, and how the 24 V controller is set up once the gate is standing.

Installed bifold gate between pillars

Before the gate arrives

  1. Check the posts

    Post foundations must be level and plumb; the gate needs no ground rail.

  2. Bring power

    Independent switch with a 6 A breaker, proper grounding, 24 V supply rated 10 A or more.

  3. Plan cables

    Signal lines go to the master unit only; the slave needs power, motor and alarm light lines.

  4. Clear the area

    Keep children and non-staff away during installation and testing.

Motor and crank arm on a bifold gate post

Commissioning checklist

Set master and slave units, run the closing self-check, then adjust open and close limits. After the self-check the gate must complete two full cycles before obstacle rebound is active.

If the gate reverses unexpectedly, raise the rebound force setting L-12. If it misses a limit, adjust L-9 or L-6.

  • Use only original sensors and parts
  • Show the owner the manual release
  • Hand over the manual after commissioning